LANSING NORTHWEST RELIEF SEWER PROJECT UPDATE

Weather permitting on Fri., Aug. 16, 2019 Linaweaver Construction will begin clearing and tree removal along the path for the Northwest Relief Sewer Project. Please see attached map.

Once clearing operations are complete, pipe installation will begin and continue until approximately Nov. 1, 2019. The remaining work on the west side of K-7/Main St. and through the Great Life Golf Course will follow shortly thereafter and continue until the spring of 2020. Affected residents that have a sewer easement on their property will be contacted directly by the contractor and/or City staff.

There are no scheduled or anticipated road closures during the phase of construction on the east side of K-7/Main St. The City asks for your patience and cooperation during construction. Periodic project updates will be provided when available.

For more information, contact Wastewater Utility Director Anthony Zell, Jr. at 913-727-2206 or azell@lansingks.org

Map
Facebook Twitter Email